Old commissary to go 'green'

  • Published
  • By Monica Mendoza
  • 21st Space Wing Public Affairs
The former commissary building here is about to be deconstructed.

Project engineers said to think of it as construction in reverse, as crews methodically dismantle the 90,000 square-foot building.

Deconstruction is the "green" approach to tearing down old buildings. The idea is to pull apart the building, preserving at least 50 percent of the material to be reused and recycled and to minimize the amount of material taken to landfills. It's different from the old way of demolition when a wrecking ball whacked the building and all of the material was hauled to a dump site.

"We will go through the entire building and look for salvageable materials -- those will be light fixtures, electrical boxes, chairs, furniture -- anything that has salvageable value," said Kevin Spala, the senior project manager with Cape, a California company heading up the $640,000 demolition project.

Crews are scheduled to mobilize Jan. 10 for the project, which is expected to be complete by mid-April.

First, the crew will remove hazardous material, including asbestos, which is expected to take two weeks. Then, the crew will make three piles: material that can be re-used; material that can be recycled, such as pipe and wire; and material to deliver to waste management.

Deconstruction is a Leadership in Energy and Environmental Design directive, said Russell Henderer, an Air Force Center for Engineering and the Environment project engineer. AFCEE has a three-person team in Colorado Springs, Colo., to oversee Air Force projects at all area bases. Mr. Henderer will oversee the commissary demolition project to ensure it follows the LEED goals of preserving building material.

LEED is an international "green" building certification system that encourages the practice of creating structures and using environmentally responsible processes, including the deconstruction of buildings.

"It's being a good steward of what we have for the environment," Mr. Henderer said.

The former commissary building, built in 1974, was old and the roof leaked, resulting in areas of the warehouse flooding at times, said Fred Brooks, a 21st Civil Engineer Squadron civil engineer.

"The most challenging part of the logistics of it all is making certain that we minimize impact to the base operations as a whole," Mr. Spala said. "And ensuring that the health and safety of the workers and the general public are in no way impeded."