Skip to main content (Press Enter).
U.S. Air Force Logo
News
Photos
Week in Photos
Air Force TV
Commentaries
Features
Art
About Us
DAF Executive Order Implementation
Air Force Senior Leaders
SECAF
CSAF
CMSAF
Biographies
Fact Sheets
50 Years of the CMSAF
Adjunct Professors
Air Force Strategic Documents
Arctic Strategy
Empowered Airmen
Careers
AF Federal Advisory Committees
AF 75th Anniversary
Policy Updates
AF Content Management
Contact Us
AF Sites
Site Registration
Events 2025
COVID Reinstatement
DLE
DAF Entertainment Liaison Office
Secretariat of the Air Force
DAF Chief Information Officer (SAF/CN)
International-Affairs (SAF/IA)
Energy Installations Environment (SAF/IE)
Financial Management (SAF/FM)
Air Force
Freedom 250
Policy Updates
Newsroom
BIOGRAPHIES
AF Senior Leaders
Playlist:
Search Results
FEATURED VIDEOS
Video by Samuel Weldin
Player Embed Code:
Share
Embed
Download
Transformer Installation Timelapse at Fort Randall Dam
U.S. Army Corps of Engineers, Omaha District
Nov. 6, 2023 | 0:35
October 11, 2023, the U.S. Army Corps of Engineers, Omaha District's contract partner Koontz Electric Company, Inc. installed the last of four new three-phase generator step-up transformers at the Fort Randall Dam Project in Pickstown, South Dakota.
This modernization and necessary upgrade is expected to increase the energy capacity at the dam from 320 megawatts to 400 megawatts, or a power increase from approximately 167,000 homes to 209,000 annually.
GSU transformers serve as the vital connection between the power plant and the transmission network, at times operating at maximum capacity around the clock. They must be constructed to endure intense thermal stress while operating with the upmost reliability.
This project replaces the original GSU transformers due to age and the need for increased transformer ratings to support the upcoming enhancements to the turbines/generators at the Fort Randall Project. This immense undertaking includes not only placing the new transformers, but also positioning them, connecting them to the power and control systems of the power plant, and setting up oil containment.
Koontz Electric was awarded the installation contract for $10.3 million, and they are on track to finish the work by November 2023. PAF Electrical Inc. secured the $7.9 million supply contract for the three-phase packaged GSU transformers. These transformers were manufactured in Germany, shipped to Galveston, Texas, transported by rail to Parkston, South Dakota, and finally delivered for installation at Fort Randall.
More
Tags
dams
Omaha District
Hydropower
USACE
More
Up Next
Now Playing
Transformer Installation Timelapse at Fort Randall Dam
1:55
Hydraulic models guide design of Garrison Dam spillway, mega dam safety project
1:43
Omaha District towboats set to power up with new engines for 2026
2:28
Conservation programs improve outlook of threatened piping plover
2:13
Paddler stops at Garrison Dam during coast-to-coast canoe trip
1:47
Garrison Dam Spillway Modification Update: August 2025
2:15
Sheridan celebrates creek revival, eyes downtown transformation
2:10
AH: Morning Quarters: July 14th
1:33
USSTRATCOM Commander Speaks To Team Whiteman During Omaha Trophy Presentation
1:35
Out with the old, in with the new: Bulkhead gates at Gavins Point Dam replaced for the first time
2:00
Pacific News: November 22, 2024
1:59
Energy experts converge for annual energy efficiency workshop
1:00
AFN Naples InFocus
1:30
What is D-Day?
5:07
USACE and MECA Partnership
More Videos